• Construction of a 2600 m2 workshop with a 730m2 office block which comprises of ablutions, eating area and two kitchens. • Supply material, fabrication, sand blasting, painting, delivering to site and erection of 125 ton steel structure. • Installation of 3200 m2 of 0.8mm Chromadeck IBR Roof sheets • Installation of 1500 m2 of 0.6mm Chromadeck IBR cladding sheets • Supply office furniture • Supply, Install and commission Gorman Rupp T3A3S Bare Shaft Pump • Construction of water and sewer reticulation. • Casting of 700 m3 of reinforced concrete. • Paving 1300 m2 with heavy duty interlocking bricks • Painting of 2500 m2 floors with epoxy flooring paint. • Installation of plumbing, electrical and mechanical works • Installation of two 20 ton overhead cranes